TABUK, Kalinga - The Kalinga Geothermal Project (KGP) is on track to complete the exploration phase with the drilling of two slimhole wells.
The Department of Energy (DOE) awarded the Renewable Energy Geothermal Service Contract to proponents Aragorn Power and Energy Corporation (APEC) and Guidance Management Corporation (GMC) on March 25, 2010 with a contract area of 26,139 hectares, spread out over the municipalities of Pasil, Lubuagan and Tinglayan.
Exploration drilling
To implement the exploration drilling, two well pads were completed including construction of access roads, improvement of national road choke points and implementation of geohazard mitigation measures.
The LF 230 coring drill rig and other drilling equipment were successfully mobilized and transported to the project site in Balatoc, Pasil with the cooperation and support of the local government units and concerned communities.
Victor Dugan of the KGP project team said that the exploration drilling has provided employment for over 50 local residents to work in various capacities.
To date, the project proponents have logged 350,000 man-hours of injury- free operations.
The project team has made an effort to engage and dialogue with the local leaders and host communities in the course of implementing the various exploration activities. These are designed to ensure that local stakeholders are informed on the status of the project and emerging issues are discussed and resolved freely and openly.
Support for local development
The community development projects provided under the individual memorandum of agreement have likewise been delivered to the eight ancestral domains namely Balatoc, Colayo, Dalupa-Ableg, Guina-ang, Dangtalan, Uma, Bangad and Tongrayan.
The KGP initiated the Kalinga Geothermal Scholarship Program in school year 2010-2011 to provide scholarship grants and educational assistance to deserving youths from the eight ancestral domains within its contract area.
As of school year 2019-2020, the program has extended scholarships to 351 grantees and produced 221 graduates in various courses. Five scholar graduates in engineering and geology have been hired for the project.
Compliance to government permits
The KGP has been compliant with the required government permits including the Certificate of Non-Coverage secured from the Department of Environment and Natural Resources, and the Special Land Use Permit covering three well pads, and water permits from the National Water Resources Board.
In keeping with the Memorandum of Agreement with the indigenous cultural communities, a joint monitoring team has been constituted with representatives from the National Commission for Indigenous Peoples, Provincial/Community Environment and Natural Resources Offices, the council of elders, and the concerned provincial, municipal and barangay local government units.
Republic Act 9513, otherwise known as the Renewable Energy law, aims to accelerate the exploration and development of renewable energy resources as well as to increase the utilization of renewable energy. The law further aims to institutionalize the development of national and local capabilities in the use of renewable energy systems, and to promote its efficient and cost-effective commercial application by providing fiscal and non-fiscal incentives.
The way forward
Dugan said that there are various phases of geothermal exploration and development which, with the successful completion of the current exploration drilling, will hopefully allow for the declaration of commerciality and eventual field development.
He said that the results from resource assessment studies and exploration drilling will serve as basis in determining commerciality of the project.
Energy Project of National Significance
The DOE awarded the Kalinga project a Certification as Energy Project of National Significance (CEPNS).
The KGP holds the distinction of being the first Renewable Energy Project to be granted a CEPNS by the DOE.
There are eight existing Geothermal Power Plants in the Philippines with total installed capacity of 1,918.19 megawatts, the biggest of which is the 722.68 MW Leyte Geothermal Power Plant. (JDP/PAB-PIA CAR, Kalinga)
Get a daily dose of Malaysia Sun news through our daily email, its complimentary and keeps you fully up to date with world and business news as well.
Publish news of your business, community or sports group, personnel appointments, major event and more by submitting a news release to Malaysia Sun.
More InformationDELHI, India - Dozens of people have died in a fire in a large factory in Delhi.Fire engines streamed through ...
HYDERABAD, India - Four men accused of the rape and murder of a 27-year old woman veterinarian in Hyderabad, India ...
Islamabad [Pakistan], Dec 9 (ANI): Pakistan firebrand politician Maulana Fazlur Rehman on Sunday claimed that in Pakistan, the Prime Minister ...
Rupendehi (Nepal), Dec 9 (ANI): The sixth day of joint military exercise between India and Nepal in Nepal's Rupendehi district ...
Washington [US], Dec 9 (ANI): A rally was organised outside Pakistan embassy in Washington on Sunday to protest against Islamabad ...
London [UK], Dec 09 (ANI): A group of people on Sunday held protests outside Avenfield flats where former Prime Minister ...
NEW YORK, New York - A robust jobs market in the U.S. may help the country avoid a recession. Figures ...
TEHRAN (Tasnim) - China Friday said it had taken 'reciprocal' measures against US diplomats in the country, who will have ...
SYDNEY, Australia - Stocks in Asia made a welcome return to the black on Friday, to close out what has ...
BEIJING, China - The Asian Development Bank (ADB) has approved a $300 million results-based lending program with private sector involvement ...
NEW YORK, New York - U.S. stock markets made minor gains on Thursday as speculation over the outcome of trade ...
Beijing [China], Dec 8 (Sputnik/ANI): The bilateral trade between China and the United States decreased by 15.2 per cent in ...